Run IOS-XE operating-system campaigns

For device operators, planners and approvers. An IOSXESoftwareRollout changes the device operating system through manager-created IOSXESoftwareUpgrade leaves. It is separate from scheduling application Pods and is currently IOS-XE-specific.

Before creating a campaign

  • Complete managed enrollment, with current device/Node identity, topology and worker-revision observations.
  • Use the matching reviewed v2026.11.1 CRDs, admission policies, chart, manager and workers. The staged activation, network-evidence and recovery extensions are introduced in November; update October installations before using them. Check release records for artifact availability.
  • Obtain the separately delegated planner and approver roles described in the authorization reference.
  • Qualify the exact image/hardware cohort, device service behavior and recovery path. An accepted topology label or heartbeat does not prove network continuity.
  • Keep BlockIfRunning unless the separate PDB-aware drain procedure has been deliberately enabled and qualified for these workloads.

The sequence is: enable the mutation profile, configure trusted image sources, review the plan and its optional gates, obtain exact-plan approval, then observe execution and settlement. Preparation without activation has a separate approval boundary described below.

1. Enable OS mutation

Enable the existing device-side upgrade executor separately:

gnoi:
  disabled: false
  enableSoftwareUpgrade: true

topology.enabled never grants software-mutation authority by implication. The rollout controller and its manager/worker mutation RBAC are inactive until both gNOI gates above are enabled. Read-only observation of retained leaves continues after disablement so an unsettled operation remains fenced. Keep gnoi.enableWriteClass=false: the managed Phase 2 coordinator rejects generic IOSXEOperationalAction because those operations do not yet implement the campaign reservation, claim, and maintenance-session contract. On an enrolled managed device, direct or unmarked IOSXESoftwareUpgrade objects are ignored. Submit an IOSXESoftwareRollout; the manager creates retained, immutable, UID/reservation-bound leaves only after admission succeeds.

Secure gNOI and image-source prerequisites

Complete the IOS-XE secure gNXI configuration, password-metadata or mTLS trust, and gNOI OS provisioning described in IOS-XE upgrade and downgrade runbook and gNOI software lifecycle design. Managed topology does not weaken or replace those controls.

For a dedicated verified gNOI trust bundle, the Kubernetes object uses a same-namespace Secret:

apiVersion: v1
kind: Secret
metadata:
  name: c9k-a-gnoi-tls
  namespace: network-devices
type: Opaque
data:
  ca.crt: BASE64_CA_PEM
  tls.crt: BASE64_OPTIONAL_CLIENT_CERT_PEM
  tls.key: BASE64_OPTIONAL_CLIENT_PRIVATE_KEY_PEM
---
apiVersion: cisco.vk/v1alpha1
kind: CiscoDevice
metadata:
  name: c9k-a
  namespace: network-devices
spec:
  # ...normal device fields...
  gnoi:
    port: 9339
    transportSecurity: tls
    tls:
      secretRef:
        name: c9k-a-gnoi-tls

ca.crt is required; tls.crt and tls.key must be supplied together when mutual TLS is used. Keep private keys in Secrets, never ConfigMaps or rollout specs.

The managed campaign API pins one image digest and family and accepts up to 16 named existing artifact endpoints. Each endpoint is either:

  • anonymous HTTPS with verified TLS and no URL credentials; or
  • SFTP with an endpoint-bound Secret and verified knownHosts data.

Scoped endpoints select protected CiscoDevice.metadata.labels; every selector key must be listed in administrator requiredTopologyKeys. A distribution.cisco.vk/cache-domain label is the recommended source-locality key. It is protected by admission and may define a transfer-budget domain, but cannot be projected to a Node. The lowest numeric priority among matching scoped endpoints wins. Equal-priority matches fail planning. Exactly one unscoped catch-all is required and is considered only when no scoped endpoint matches. Every endpoint serves the single campaign-wide SHA-256 identity; CVK does not silently fail over after approval.

IOSXESoftwareRollout remains a v1alpha1 API. The published October baseline uses plan.image.sources and per-target frozen source snapshots; the earlier development preview used plan.source. There is no conversion webhook between those shapes. A cluster that ran that older preview must first settle and export its rollout evidence, remove the obsolete preview objects, and upgrade the CRD and controller together. Do not deploy an older controller over stored objects whose source schema it cannot interpret. The staged, network-evidence and recovery contracts introduced in v2026.11.1 also require matching CRDs, admission policies, manager and workers.

Managed source resolution rejects redirects, environment proxies, URL userinfo, queries/fragments, unsafe or mixed DNS answers, loopback, link-local, multicast, unspecified, metadata, and other special-use destinations. Private-address HTTPS is rejected. Private SFTP is allowed only with an endpoint-bound Secret. This stricter policy applies to manager-created managed leaves; standalone legacy leaf behavior remains compatible.

An SFTP Secret has this shape:

apiVersion: v1
kind: Secret
metadata:
  name: site-a-image-source
  namespace: network-devices
  labels:
    cisco.vk/purpose: software-image-source
type: Opaque
stringData:
  allowedScheme: sftp
  allowedHost: images.site-a.example.net
  allowedPort: "22"
  username: image-reader
  privateKey: |
    -----BEGIN OPENSSH PRIVATE KEY-----
    REPLACE_ME
    -----END OPENSSH PRIVATE KEY-----
  knownHosts: |
    images.site-a.example.net ssh-ed25519 REPLACE_ME

The manager freezes each target's selected source, priority, URL, digest, and Secret UID into the plan and managed leaf. In-place credential rotation under that UID is allowed, but every use revalidates source purpose, endpoint, and trust policy. Delete/recreate changes the UID, fences new claims, and requires a newly frozen and approved rollout. Transient resolution failures retry only that frozen endpoint within the install deadline. A permanent failure or expired deadline fails the leaf and fences further campaign admission; it never falls through to a different mirror under the approved hash.

2. Review disruption, risk and network gates

These controls apply before approval. Keep their operational constraints with the plan; they are not implied by Kubernetes application-placement rules.

Administrator policy may also define up to 16 disruptionProtections. Each rule has a DNS-label name, a reason (CriticalService or SingletonPath) and a non-empty Kubernetes label selector whose keys are included in requiredTopologyKeys. These rules are prohibitions, not hints: a matching CiscoDevice cannot enter the current combined software lifecycle. The manager checks them while freezing the plan and again from current protected labels before admission. Adding or changing a rule changes both policy hashes and requires re-planning; already-claimed physical work remains under observation instead of being abandoned. The rule also blocks image preparation; PrepareOnly does not bypass administrator disruption protections. Never infer redundancy merely from a label—use qualified path and service evidence before removing a singleton or critical-service protection.

Administrator policy may additionally define up to 16 riskGroups. Each group has a DNS-label name, a non-empty Kubernetes selector restricted to requiredTopologyKeys, maxConcurrentTransfers, and maxUnavailable. It may also set maxAggregateTransferBytesPerSecond for a known shared distribution or forwarding path. A device may match multiple groups. The frozen plan records each target's sorted groups and a SHA-256 digest of the complete relevant physical membership. Before admission, the manager recomputes that membership and requires an exact match. In the same ledger compare-and-swap used for global/domain budgets, it counts unhealthy non-target members and reservations from every campaign against every applicable group. All groups must pass. Changing a selector, budget, or membership requires a new plan and approval. Risk groups are explicit operator constraints; they do not prove that a forwarding path is redundant or healthy.

For each matching group with an aggregate byte ceiling, the manager derives a conservative per-transfer share by dividing that ceiling by the group's maxConcurrentTransfers. The lowest share across overlapping groups is frozen in the approved target and copied into the immutable leaf. The worker enforces that value independently while materializing remote image bytes and while streaming the verified image through gNOI OS.Install. Cache hits skip the source-network segment but never the device segment. A resolver that cannot enforce an opted-in source limit is rejected before install; an omitted limit preserves existing behavior. An ordinary paced leaf requires the rollout-byte-pacing-v1 manager/worker admission protocol, which makes a rolling deployment fail closed when an older worker does not understand the new rate field. The ceiling applies only to CVK-owned traffic and does not replace measured headroom or service-path validation. Ensure the install timeout and maintenance window accommodate the paced image size plus device validation and activation.

To opt into the network gate, require complete evidence and name the exact interfaces and adjacencies that must be healthy:

spec:
  plan:
    strategy: Reload # NoReboot is a combined strategy, not a proven prepare-only hold
    health:
      network:
        enabled: true
        requireCompleteEvidence: true
        requiredInterfaces: [GigabitEthernet1/0/1]
        requiredNeighbors: [core-a]
        requireInterfacesUp: true
        requireNeighborsFull: true

The network-management worker publishes only a bounded producer sample under CiscoDevice.status.healthObservation.network; it does not publish raw CLI, credentials, or arbitrary topology. That raw field is not rollout authority. The manager validates the exact device incarnation, physical-identity hash, current worker revision and Pod UID, positive sequence, original collection interval and duplicate-free interface/adjacency identities. Only then does it copy the sample to the manager-owned CiscoDevice.status.healthObservation.acceptedNetwork. Native admission lets the worker change the raw field but rejects worker changes to the accepted field. Rollouts consume only the accepted copy and calculate freshness from the start of collection, so a late status write or manager restart cannot refresh old evidence.

Missing, unaccepted or stale evidence blocks the rollout with a reason such as EvidenceMissing, EvidenceStale, AlternatePathUnavailable, or DeviceIdentityMismatch. The gate is nil by default, so existing campaigns retain their behavior. Physical idle-state CLI comparison is recorded, but loaded directional-rate accuracy and redundant-supervisor health remain unqualified until their declared E02 test fixtures exist; these signals must not be inferred from labels or an unrelated successful device read.

3. Check runtime compatibility

Before replacing controllers, settle active older staging and network-gated campaigns using their compatible runtime. Do not edit immutable leaves or protocols, erase claims, or assume an arbitrary Helm rollback is safe. Apply new CRDs before the matching manager/workers, with new campaigns paused. The exact released-manager protocol check, actual released-manager Pod's rejection of the newer native admission contract, and stored neighbor map-to-atomic migration now pass. Interrupted deployment and the wider reverse-manager/rollback matrix remain merge gates; see the compatibility follow-up.

The protocol reference explains the staged, network-evidence and pacing contracts. Settle old claimed work with its compatible runtime before replacing it; a chart rollback is not a recovery shortcut.

4. Submit, review, and approve

Start from examples/topology/iosxe-software-rollout.yaml. Create a new object for every upgrade or downgrade; executable intent is immutable. A downgrade is the same workflow with a qualified lower targetVersion and its exact compatible image/digest.

The creator must have the deliberately unbound rollout-planner role, and spec.plan.requestedBy must exactly equal the authenticated Kubernetes username. A campaign must start with neutral spec.control.revision: 0.

Edit and review the example locally, replacing its identities, image digest, sources, targets, cohorts and time fields with the intended values. Then submit that reviewed manifest using the planner's Kubernetes credentials:

kubectl apply -f examples/topology/iosxe-software-rollout.yaml

The observation and approval examples below assume the manifest keeps the name cat9k-17-18-4 in network-devices; substitute the exact chosen coordinates if you renamed it. Submission creates the plan, not permission to mutate the device.

After creation, wait for AwaitingApproval and review the complete frozen target/source/policy snapshot:

kubectl get iosxesoftwarerollout cat9k-17-18-4 \
  -n network-devices -o yaml

PLAN_HASH="$(kubectl get iosxesoftwarerollout cat9k-17-18-4 \
  -n network-devices -o jsonpath='{.status.frozenPlan.hash}')"
printf '%s\n' "$PLAN_HASH"

Review the qualification cohorts as part of that approval. Every selected device must carry a protected operations.cisco.vk/qualification-cohort=<hardware-capability-class> label. spec.plan.canaries must contain one entry whose name exactly equals each distinct cohort value, with at least one explicit target device in that entry. The manager rejects missing cohorts, mismatched membership, duplicate canary assignments, and a cohort without a canary. It freezes and revalidates the cohort on every target, so later device-label or generation drift requires a new plan. This prevents one successful hardware class from implicitly qualifying a different class; incompatible hardware/image combinations need separate qualified images or separate campaigns. The label is an administrator assertion backed by lab evidence, not hardware auto-discovery.

Approval is append-only and authorizes only that exact hash. The approver must have the separately delegated rollout-approver role, and approvedBy must match that request's authenticated identity:

APPROVER="$(kubectl auth whoami -o jsonpath='{.status.userInfo.username}')"
APPROVED_AT="$(date -u +%Y-%m-%dT%H:%M:%SZ)"

kubectl patch iosxesoftwarerollout cat9k-17-18-4 \
  -n network-devices --type=merge \
  -p "{\"spec\":{\"approval\":{\"planHash\":\"${PLAN_HASH}\",\"approvedBy\":\"${APPROVER}\",\"approvedAt\":\"${APPROVED_AT}\"}}}"

Do not copy the approval patch under a different identity. Approval is bound to the live frozen hash and authenticated approver. Changed target identity or an incompatible policy requires a new plan; compatible policy edits can only tighten active limits. See policy transitions for the exact rules. Never edit a frozen plan or immutable child to repair drift.

Separate preparation from activation

For a qualified staged workflow, start from the PrepareOnly campaign example. Replace every placeholder and use the normal planning and approval process above. PrepareOnly does not authorize activation: it retains immutable preparation receipts and device ownership.

Only after every frozen target has completed preparation, an operator with the separate activate permission may construct the activation approval patch from the exact live plan, device/leaf UIDs and receipt hashes. Use its server-side dry run before applying the append-only approval, within a qualified maintenance window. Do not invent or copy receipt identities. See the staged lifecycle reference for the contract and unused-preparation recovery if activation will not proceed. A retained receipt blocks ownership retirement.

5. Observe admission and execution

For each target, the manager checks:

  • same namespace and frozen CiscoDevice UID and generation;
  • driver XE, image-family match, unique declared physical identity, exact Node UID, projection hash, and worker protocol;
  • deterministic source selection still resolves to the exact frozen endpoint and Secret incarnation;
  • no administrator CriticalService or SingletonPath disruption protection matches the current protected device labels;
  • fresh device and Node health, including current producer observations for NodeIdentityReady, TopologyReady, and GNOIConfigurationReady;
  • the selected workload policy: BlockIfRunning requires no live Kubernetes or device workload, while Drain requires the exact bounded eligibility, PDB, session, teardown, replacement-readiness, and inventory proofs in the drain procedure;
  • global and every independent domain transfer/unavailability ceiling;
  • every matching administrator risk-group transfer/unavailability ceiling, including non-target health and reservations from other campaigns;
  • the strictest frozen risk-group byte-rate share on every applicable image transfer segment;
  • existing unhealthy or maintained fleet members, including non-targets; and
  • no conflicting device mutation.

Campaign health is intentionally narrower than end-to-end network assurance. Baseline gates prove a fresh bound Node Ready heartbeat, manager-owned identity/topology/gNOI configuration observations and the leaf lifecycle result. The optional network gate above additionally requires its exact accepted interface/adjacency evidence. Neither establishes production packet forwarding, loaded directional-rate accuracy or complete stack/supervisor health. Qualify those operational requirements independently; absent evidence is not a pass.

The final worker-side workload check is fail closed. Under BlockIfRunning, terminating Kubernetes Pods still block; retained Succeeded or Failed Pods alone do not. Any live app or orphan returned by the device driver blocks, and a missing callback or inventory error blocks rather than assuming the device is empty. Under Drain, only an exact selected teardown in the active session may run, and its complete post-delete device inventory becomes durable worker evidence before promotion. The provider coordination contract is driver-neutral for future platforms, although campaign registration and the software lifecycle remain explicitly IOS XE only.

Campaign phases are AwaitingApproval, Paused, Executing, Soaking, Cancelling, Succeeded, Failed, and Cancelled. The explicitly frozen canary from every qualification cohort is wave zero; non-canaries are wave one and remain ineligible until every cohort's canary has settled its post-operation checks. Budgets still serialize admission within a wave. A completed leaf is not settled immediately: its effective manager-authenticated health time, including the snapshotted Node heartbeat and required producer observations, must be strictly later than leaf completion. A newer live heartbeat alone cannot satisfy this gate. The device and Node must then remain continuously healthy for the configured canary or wave soak interval. A stale or unhealthy observation resets progress rather than consuming an elapsed timer. status.counts.cancelled distinguishes targets fenced by cancellation from failed targets.

Before a new device RPC, the worker commits an append-only, stage-specific mutation claim bound to the current reservation, policy epoch, and control revision. It must first publish a worker-control acknowledgement of that same epoch and grant. An ambiguous install, activation, or rollback result keeps the reservation and pauses safe progression until an operator reconciles physical state.

rollbackOnFailure: true is the existing limited leaf attempt to reactivate the previously observed version after post-verify failure. It is not a fleet-wide transaction and is not a substitute for a separately planned downgrade campaign.

The health and reservation reference explains freshness, accepted observations and claims. A timer or Lease expiry never proves that an accepted device mutation completed.

6. Pause, resume, or cancel

Only the rollout-planner role carries the custom control permission. Every change increments revision and binds requestedBy to the authenticated caller. Example pause:

REQUESTER="$(kubectl auth whoami -o jsonpath='{.status.userInfo.username}')"
REQUESTED_AT="$(date -u +%Y-%m-%dT%H:%M:%SZ)"

kubectl patch iosxesoftwarerollout cat9k-17-18-4 \
  -n network-devices --type=merge \
  -p "{\"spec\":{\"control\":{\"revision\":1,\"pause\":true,\"requestedBy\":\"${REQUESTER}\",\"requestedAt\":\"${REQUESTED_AT}\",\"reason\":\"change freeze\"}}}"

Resume with a larger revision and pause:false. Cancel with a larger revision and cancel:true; cancellation is terminal. Pause/cancel prevents future claims but cannot undo an RPC already accepted by the switch. Inspect status.control.requestedRevision, effectiveRevision, pausePending, and cancellationPending rather than assuming a patch is immediately effective.

Verify the outcome and continue

Use campaign and leaf observation to confirm the requested control became effective, each device outcome is conclusive, current post-mutation health and the required continuous soak passed, and reservations settled. A successful transfer alone is not a completed upgrade. For preparation, retain the receipts and ownership until separately approved activation or verified invalidation; do not expect a prepared device to become unowned.

For an uncertain result, preserve evidence and use the recovery guide. A planned downgrade requires a new approved campaign; it is not a rewrite or replay of the previous one.